i just wanted to let everyone know how things are going with the building.
last week the framing crew got the whole structure up, with plywood outside and tyvek wrapping it all up before it started raining.
we are waiting for the doors and windows to arrive - they were a little back ordered, but should be here around thanksgiving. The roof might happen before the windows get here.
It's likely that Maria will be here for a few weeks starting in December, and I'm hoping she will be able to lead volunteers to do things like insulating, drywalling, designing the interior - but a lot will depend on what gets done before then.
There's a lot to figure out - materials, money, carpentry, schedules, design - let me know if you want to be a part of any of this.